Bessemer Alabama Parking Lot Fiasco Project
So, Update from the parking lot fiasco in Bessemer AL. Things are starting to turn around and progress is being made. It’s took 2 1/2 days to clean off the dirt to see exactly what we were dealing with. Seems as if it was a combination of poor soils that retain moisture and can’t drain, water coming from the adjacent property (now fixed) and poor compaction (due to poor soils). The wheel rutting of the asphalt allowed water to pool and further compromise the subgrade. We undercut some places 3ft to get past the wet nasty dirt that was deflecting and pumping. We then replaced the dirt with 3 to 4” clean stone and then topped it off with 6” of dense grade base limestone. We also got the next section undercut and ready for stone. Check out the pics to see the progress.
Slicking it off and making it shine!!
Update Coming Soon……